What to Expect
- Removal of curbs from Macomb Place to enhance accessibility for those with mobility issues
- Relocation to the western side of Macomb Place and expansion of the fountain stage, clearing the view of the street and allowing plows access without tearing up curbs and sidewalks due to the winding road
- A new mural
- Lighting upgrades
- Underground infrastructure upgrades for sewer and electrical
- Repaving and adding pay stations to the New Street lot
Frequently Asked Questions
-
How is this project being funded?
The DRP is funded by a $3.5 million grant from the U.S. Department of Housing and Urban Development, secured by Representative John James; $813,000 from the Michigan Economic Development Corporation; $800,000 from the City of Mount Clemens’ general fund; $334,000 from the American Rescue Plan Act; and $200,000 from the Downtown Development Authority’s reserve funds.
-
When will the project be complete?
Construction will be completed on November 1st, 2025. Greenery and amenities will be added in Spring 2026.
-
Will pedestrian walking access to downtown businesses be maintained?
Yes, pedestrian walking access will be maintained everywhere in Downtown Mount Clemens throughout the project.
-
What will happen to the DDA’s annual events during the construction period?
All major events, including the summer concert series, the art & craft fairs and more will still occur, though the location may differ based on the event’s specific needs. Please follow our social media pages for more information about our upcoming events.
-
What is the best way to stay up-to-date with the project?
DRP project updates will be continuously posted to our social media outlets. You can follow us on the following platforms:
- Instagram at @downtownmountclemens
- Facebook at Downtown Mount Clemens
- X at @downtownmountclemens.
-
Where should I park as an alternative to Macomb Place?
All other streets will have parking available, as will our city parking lots. The closest lots to Macomb Place are the Roskopp and New Street lots.
-
Will the city offer free parking during construction?
The city offers free parking on all weekends and after 6 p.m. on weekdays.
-
Are all patios and outdoor dining now removed from Cherry Street and Macomb Place?
All outdoor dining patios on Cherry Street or Macomb Place will be closed during construction but will reopen once construction is complete.
Notices & Updates
Week of November 24th – Completed construction activities listed below:
- Brick paver installation working in the south mall corridor from Macomb Place to the Roskopp entrance.
- Electrical conduit installation for existing wires to new panel box location.
- Entry sign foundation installation near Roskopp Entrance, poured concrete foundations on Wednesday.
- New Street Parking Lot Work – No work took place.
No construction progress meeting took place due to Thanksgiving holiday.
Two-Week Outlook
Week of December 1st – Construction Activities listed below.
- Brick paver installation working in the south mall corridor from Macomb Place to the Roskopp entrance.
- Sign post installation, street signage planned to be installed later in week. Drainage structure trap installation on Macomb Place.
- Pavement striping scheduled with PK Contracting to complete first application pavement markings on project.
- Rock bench delivery and placement into locations shown on plans.
- New Street Parking Lot Work – Fence installation around electrical boxes near brick wall.
Friday, December 5th – Next progress meeting in DDA Office at 9:00am.
Week of December 8th – Construction Activities listed below:
- Brick paver installation finishing in the south mall corridor near the Roskopp entrance.
- Entry sign arch installation on south side near Roskopp entrance.
- Pulling electrical wiring through conduit and light pole installation scheduled with Rauhorn.
- Pavement striping scheduled with PK Contracting to complete first application pavement markings on project.
- Macomb Place opening this week, will coordinate with the Contractor for general cleanup and completing final items before opening the road.
- New Street Parking Lot Work – EV Charger Installation, if not completed prior.
Wednesday, December 10th at 2:00pm – Next Business Owners Meeting
What Will This Look Like?
Check out the renderings below, courtesy of Anderson, Eckstein & Westrick, Inc.!

